Project

Optimising an Existing Solar PV System with Battery Storage

An existing 65 kWp ground-mounted solar PV installation upgraded with a 50 kW Sigenergy hybrid inverter and 96 kWh battery energy storage system, increasing on-site self-consumption while maintaining compliance with the site's 50 kW DNO Connection Limit.

PROJECT SCOPE

How SJ1 Renewables Supported This Project

Assessment
Generation and consumption analysis
Design
Battery sizing and system integration
G99 & G100
DNO application and export limitation
Commissioning
Battery storage installation and compliance testing
Existing commercial solar PV installation with battery storage system

Project Overview

A mixed arable and sheep farm in North Devon operates alongside several independent manufacturing businesses occupying commercial units on the estate. Together these create a varied three-phase electrical demand throughout the day.

The estate already benefited from a well-performing 65 kWp ground-mounted solar PV system. Monitoring software provided detailed information on electricity generation, import and export, allowing performance to be reviewed in real time.

The monitoring data showed that surplus electricity was regularly being exported during periods of strong solar generation before the estate later returned to importing electricity as demand exceeded generation.

The site also operated under a 50 kW Connection Limit (CLS) imposed by the local Distribution Network Operator (DNO). Any battery storage solution therefore needed to maximise on-site energy use while ensuring the site's export to the grid never exceeded the approved limit.

The objective was not simply to install battery storage, but to deliver a fully compliant engineering solution that improved self-consumption, reduced imported electricity and satisfied the required DNO and grid connection requirements.

SYSTEM OVERVIEW

Project Highlights

65 kWp
Existing solar PV
50 kW CLS
DNO Connection Limit
96 kWh
Battery storage
G99 & G100
Grid connection compliance

Engineering Assessment

SJ1 Renewables reviewed the site's generation profile together with import, export and daily consumption patterns. Analysis confirmed that the existing PV system was generating sufficient renewable electricity, but much of this generation occurred before periods of higher site demand.

A battery energy storage system was selected to capture surplus daytime generation and discharge it later as demand increased. This improves self-consumption while reducing imported electricity and low-value exports.

The proposed solution also needed to operate within the site's existing 50 kW DNO Connection Limit (CLS). This required careful integration of the battery inverter, energy management system and export limitation controls so that solar generation, battery charging and battery discharging could operate together without exceeding the permitted export capacity.

The selected arrangement provides enough charging and discharging capacity to respond quickly to changes in site demand, while avoiding unnecessary oversizing. It also provides a platform for future expansion if the estate's energy requirements increase.

Grid Connection & DNO Compliance

A key part of the project was ensuring the upgraded system complied with the requirements of the local Distribution Network Operator. SJ1 Renewables managed the grid connection process, including preparation and submission of the required G99 application for the battery storage installation.

Because the site had an approved 50 kW Connection Limit (CLS), the installation also required a compliant G100 Export Limitation Scheme. This ensures that the combined operation of the existing solar PV system, battery inverter and site demand remains within the agreed export capacity.

The export limitation system continuously monitors the site's power flow and dynamically regulates the battery inverter so that total export does not exceed the approved 50 kW limit. This allows the customer to make greater use of renewable electricity generated on site without requiring costly network reinforcement or risking non-compliance with the grid connection agreement.

Following installation, SJ1 Renewables completed commissioning, verification of the export limitation controls and the associated documentation required for DNO acceptance.

Installation

The completed installation comprises a 50 kW Sigenergy hybrid inverter, 96 kWh of battery storage and intelligent energy management integrated with the existing 65 kWp solar PV system.

The system incorporates G100-compliant export limitation controls, allowing battery charging and discharging to be coordinated with solar generation and site demand while maintaining compliance with the site's approved 50 kW Connection Limit.

The retrofit was completed around an operational agricultural and commercial site, allowing the farm and tenant businesses to continue operating with minimal disruption.

Operational Performance

The battery now charges automatically whenever solar generation exceeds site demand before discharging as electrical consumption increases later in the day.

The graph below illustrates a typical operating profile recorded after commissioning. The battery charges from surplus PV generation during the morning before reaching full capacity. As solar production reduces, stored energy is discharged to support the estate's electrical demand, significantly increasing on-site utilisation of renewable electricity.

Battery State of Charge profile
Figure 1. Battery State of Charge (SOC) over a typical operating period, demonstrating daily charging from surplus solar generation and discharge as site demand increases.

During periods of good solar production the battery routinely reaches full capacity before supplying energy back to the site throughout the afternoon and evening. This significantly reduces exported electricity while increasing the proportion of renewable energy consumed on site.

Project Outcome

The completed installation has improved the performance of the existing solar PV system by retaining renewable electricity on site that would previously have been exported. This energy is now used to supply both the agricultural operation and commercial tenants.

Actual savings will vary depending on weather conditions, site demand and electricity tariffs. However, battery storage increases the value of surplus renewable electricity by allowing it to be consumed on site rather than exported.

Using representative tariffs of 25 p/kWh for imported electricity and 5 p/kWh for exported electricity, each kilowatt-hour retained on site is worth approximately 20 pence more than if it had been exported. Based on the observed operating profile, the installation is estimated to increase self-consumption by approximately 16 MWh per year, representing an energy value improvement of around £3,200 annually.

Beyond the financial benefits, the project demonstrates how SJ1 Renewables can deliver complete engineering solutions for constrained grid connections. By combining battery storage with a fully compliant G99/G100 grid connection solution, the customer has been able to maximise on-site renewable energy use while remaining compliant with their 50 kW DNO Connection Limit (CLS).

Why Battery Storage?

Many existing commercial and agricultural solar PV installations were designed before battery storage became commercially viable. As a result, surplus electricity is often exported during periods of peak generation before electricity is imported later in the day.

Retrofitting battery storage can improve self-consumption without increasing generating capacity, allowing existing renewable energy assets to deliver greater operational and financial value. Where a site has an existing DNO export limit, a correctly designed G100 export limitation scheme can also allow battery storage to be installed without exceeding the agreed connection capacity.

Optimise Your Existing Renewable Energy System

If you already have solar PV, wind or hydro generation, SJ1 Renewables can assess your existing system and identify practical opportunities to improve performance through battery storage, system upgrades, G99 applications and G100 export limitation controls.

✉ info@sj1renewables.com